Soluna Holdings announced the completion of its 83 MW Project Kati 1 data center in Texas and secured a key regulatory classification from ERCOT. The company energized the final 14 MW of the project, bringing its total company-wide operating capacity to approximately 206 MW.
Key Details
- Project Completion: The final 14 MW at Project Kati 1 in Willacy County, Texas, has been energized, completing the 83 MW site which is dedicated to Bitcoin hosting.
- ERCOT Classification: The full 166 MW Kati campus, including the completed Kati 1 and the planned 83 MW Kati 2 AI expansion, received a conditional "Base Load" classification in ERCOT's Batch Zero interconnection process.
- Strategic Impact: The Base Load status preserves the project's interconnection capacity and exempts it from further reliability evaluation, providing a significant advantage in a crowded interconnection queue.