Power Solutions International, Inc. (PSIX) has amended its long-term supply agreement with HD Construction Equipment Co., Ltd. (HCE) to secure a supply of natural gas engine long blocks for 2027 and 2028. The amendment provides fixed pricing and a defined delivery schedule for aggregate purchases valued at approximately $121.9 million, strengthening PSIX's supply chain for its power generation systems used in data centers and other critical infrastructure.
Key Details
- Agreement Value & Term: The amendment covers aggregate purchases of approximately $121.9 million for GV22TI 22-liter natural gas engine long blocks for calendar years 2027 and 2028.
- Pricing: Establishes a fixed unit price for all specified engines ordered and shipped on or before December 31, 2028, providing price certainty.
- Payment Terms: PSIX is required to make advance payments equal to 10% of each year's contract value. The advance for 2027 volume is due by November 30, 2026, and the 2028 advance is due by June 30, 2027.
- Volume Commitment: If total purchases over the 24-month period are less than 90% of the scheduled volume, the parties will negotiate a recovery mechanism, which could include a price increase in 2029.