A Harvard-led study found that 403 U.S. hyperscale data centers that became operational between May 2024 and April 2025 use as much electricity annually as the state of Michigan. Published in Nature Sustainability, the study estimates their annual electricity use at 82 terawatt-hours. The facilities produce approximately 25.7 million metric tons of carbon dioxide.
The growth in power use is largely attributed to the rapid expansion of artificial intelligence and cloud computing. More than half of the electricity consumed by the data centers came from fossil fuels. Their emissions have reportedly tripled compared with pre-AI-boom levels.
Researchers said federal and state agencies do not separately track data center electricity use, requiring academics to reconstruct the figures. The findings raise concerns about pressure on the U.S. power grid and the climate impact of AI’s expansion.