Ontario Power Generation (OPG) says the first small modular reactor (SMR) at its Darlington site will miss its planned October 2030 operational date and exceed its initial C$7.7 billion budget. The announcement appeared in OPG’s third-quarter financial report. The reactor uses GE Vernova Hitachi’s BWRX-300 technology.
OPG attributes the delays and cost overruns to ongoing engineering challenges with the first-of-a-kind design. The challenges have affected construction execution and supply-chain performance.
OPG is working with GE Vernova Hitachi to complete the outstanding engineering work and is conducting a comprehensive assessment of the project’s cost and schedule. The revised budget and timeline are expected to be substantially completed by mid-2027.