enCore Energy received the final Production Area Authorization from the Texas Commission on Environmental Quality for its Upper Spring Creek In-Situ Recovery Uranium Project. The authorization is the last wellfield permit required to begin injection and recovery operations at the site.
The satellite plant and first wellfield are already constructed. enCore anticipates starting oxygenated water injection and uranium extraction in the first week of December.
The remaining step is approval to operate the Waste Disposal Well. The well is fully constructed, and approval is expected in December, allowing the company to ramp up to full-scale operations.