Core Scientific filed plans for a $1.3 billion data center in Quinlan, Hunt County, Texas. The Texas Department of Licensing and Regulation registered the project on November 13.

Plans call for a 341,326-square-foot data center shell and related infrastructure. Construction is slated to begin on November 24, 2026. Completion is projected for September 4, 2028.

The facility is part of a larger Hunt County campus where Advanced Micro Devices (AMD) is set to lease approximately 110 megawatts of power. It will support high-density computing for artificial intelligence and other advanced workloads.

The campus is part of Core Scientific’s strategy to expand its AI infrastructure hosting capabilities. In July, the company announced a large-scale agreement with AMD to lease capacity across multiple sites.